Rural Municipality of Meota No. 468 - Iffley Bridge Replacement
Federal contribution
$75,682
Federal share17%
of $454.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 14, 2022
2023
Built
Approved 5 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Rural Municipality of Meota No. 468
- Construction start
- Jul 1, 2023(actual)
- Construction end
- Aug 15, 2023(actual)
Also in Meota