MacLean Street Trunk Sewer - Phase I
Federal contribution
$334,307
Federal share33%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 30, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Town of New Glasgow
- Construction start
- Jun 28, 2010(actual)
- Construction end
- Nov 18, 2010(actual)
Against the original forecast
- Construction start9 months lateforecast Oct 1, 2009
- Construction end6 months lateforecast Jun 1, 2010
Also in New Glasgow
- New Glasgow Library and Pictou-Antigonish Regional Library (PARL) Headquarters Revitalization$3.9M
- Southend Sewer Separation (Phase II to IV)$1.5M
- New Glasgow Water Treatment Expansion$1.3M
- Water Transmission Line Replacement on East River East Side Road$1.2M
- Town of New Glasgow - Abercrombie Road Waterline Replacement$1.1M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27092 in the federal list. How to read these figures.