Town of New Glasgow - Abercrombie Road Waterline Replacement
Federal contribution
$1.1M
$1,059,600
Federal share40%
of $2.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 4, 2024
20232024
Built
Approved 15 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of New Glasgow
- Construction start
- Apr 17, 2023(actual)
- Construction end
- Sep 26, 2023(actual)
Against the original forecast
- Construction end2 months earlyforecast Dec 1, 2023
Also in New Glasgow
- New Glasgow Library and Pictou-Antigonish Regional Library (PARL) Headquarters Revitalization$3.9M
- Southend Sewer Separation (Phase II to IV)$1.5M
- New Glasgow Water Treatment Expansion$1.3M
- Water Transmission Line Replacement on East River East Side Road$1.2M
- East River Road water trunk transmission line renewal$815.4K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65786 in the federal list. How to read these figures.