East River Road water trunk transmission line renewal

New Glasgow, Nova Scotia

completeDrinking WaterCWWF
Federal contribution
$815,428
Federal share50%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 16, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of New Glasgow
Construction start
Aug 1, 2017(actual)
Construction end
Dec 31, 2017(actual)

Against the original forecast

  • Construction start4 months lateforecast Apr 3, 2017
  • Construction end3 months earlyforecast Mar 31, 2018

Also in New Glasgow

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47264 in the federal list. How to read these figures.