Back to projects

Dam Upgrade - Hebb's Lake

Bridgewater, Nova Scotia

completeDrinking WaterCC
Federal contribution
$906,028
Federal share33%

of $2.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 30, 2009
201020112012
Built
Program
Building Canada Fund - Communities Component
Construction start
Aug 30, 2010(actual)
Construction end
Sep 30, 2012(actual)

Against the original forecast

  • Construction start4 months lateforecast May 1, 2010

Also in Bridgewater

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27104 in the federal list. How to read these figures.