Highway 103: Ingramport to Hubbards Twinning
Federal contribution
$33.1M
$33,110,000
Federal share50%
of $66.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 25, 2017
20182020202220242026
Built
Approved 5 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Province of Nova Scotia
- Construction start
- Jul 7, 2020(actual)
- Construction end
- Mar 31, 2026(actual)
Against the original forecast
- Construction start6 months lateforecast Jan 1, 2020
- Construction end9 months earlyforecast Dec 31, 2026