Water and Sewer Expansion-Centennial Hill
Southern Harbour, Newfoundland and Labrador
Federal contribution
$143,194
Federal share33%
of $429.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2010201220142016
Built
Approved 6.7 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Southern Harbour
- Construction start
- Jun 30, 2009(actual)
- Construction end
- Oct 31, 2010(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Aug 1, 2009
- Construction end11 months lateforecast Nov 30, 2009
Also in Southern Harbour
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27108 in the federal list. How to read these figures.