Chlorination Upgrades

Southern Harbour, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$407,487
Federal share40%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
202220232024
Built
Program
Green Infrastructure Stream
Ultimate recipient
Town of Southern Harbour
Construction start
Feb 19, 2024(actual)
Construction end
Sep 30, 2024(actual)

Against the original forecast

  • Construction start3 months earlyforecast May 15, 2024
  • Construction end4 weeks lateforecast Aug 30, 2024