Back to projects

Upgrading of Water Pollution Control Plant

Smiths Falls, Ontario

completeWastewaterCC Top Up
Federal contribution
$1.4M
$1,416,667
Federal share33%

of $4.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
Jul 20, 2010(actual)
Construction end
Sep 9, 2011(actual)

Against the original forecast

  • Construction start10 months lateforecast Sep 14, 2009
  • Construction end7 weeks earlyforecast Oct 31, 2011

Also in Smiths Falls