Separation of Combined Sewer System on Lorne Street (Queen St to CPR Railway)

Smiths Falls, Ontario

completeWastewaterCWWF
Federal contribution
$422,282
Federal share50%

of $844.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
2018
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Smiths Falls
Construction start
Jul 10, 2017(actual)
Construction end
Oct 31, 2018(actual)

Against the original forecast

  • Construction end4 months lateforecast Jun 30, 2018

Also in Smiths Falls