Improvement to Ebb's Bay Road

Perth, Ontario

completeHighways and RoadsCC Top Up
Federal contribution
$432,653
Federal share33%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
Jul 6, 2010(actual)
Construction end
Oct 31, 2010(actual)

Against the original forecast

  • Construction end4 weeks lateforecast Sep 30, 2010