New HVAC system at Lanark Lodge
Federal contribution
$1.4M
$1,398,432
Federal share80%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 16, 2021
20222023
Built
Approved 3 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Corporation of County of Lanark - Lanark Lodge
- Construction start
- Jul 26, 2021(actual)
- Construction end
- Sep 30, 2023(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jun 4, 2021
- Construction end18 months lateforecast Mar 31, 2022
Also in Perth
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59457 in the federal list. How to read these figures.