Schedule
Announced and approvedJun 5, 2009
201020112012
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- City of Owen Sound
- Construction start
- Mar 4, 2010(actual)
- Construction end
- Mar 31, 2012(actual)
Against the original forecast
- Construction start7 months lateforecast Aug 11, 2009
- Construction end4 weeks earlyforecast Apr 30, 2012