Owen Sound Secondary Sewage Upgrade
Federal contribution
$15.0M
$14,955,000
Federal share33%
of $44.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 5, 2013
201220132014201520162017
Built
Approved 2.3 years before the announcement.
- Program
- Green Infrastructure Fund
- Ultimate recipient
- Corporation of the City of Owen Sound
- Construction start
- Aug 11, 2014(actual)
- Construction end
- Aug 24, 2017(actual)
Against the original forecast
- Construction start7 months lateforecast Jan 10, 2014
- Construction end9 months earlyforecast May 31, 2018
Also in Owen Sound
- Construction of Owen Sound Multi-Purpose Recreation Facility$10.9M
- Reconstruction of the Grey-Bruce Line Road$4.1M
- Marine Emergency Duties Training and Research Centre at the Georgian College Owen Sound Campus$1.7M
- Owen Sound Water Treatment Plant Filtration System Improvements$1.6M
- Upgrading of the wastewater system$1.1M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29890 in the federal list. How to read these figures.