Rehabilitation of the Hart Road Bridge
Federal contribution
$114,333
Federal share33%
of $343.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Municipality of Callander
- Construction start
- Nov 2, 2009(actual)
- Construction end
- Nov 30, 2010(actual)
Against the original forecast
- Construction end12 months lateforecast Nov 20, 2009
Also in Callander
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27240 in the federal list. How to read these figures.