Standby Power Generation

Callander, Ontario

completeWastewaterISF
Federal contribution
$100,000
Federal share33%

of $300.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Municipality of Callander
Construction start
Aug 31, 2009(actual)
Construction end
Jul 15, 2010(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 1, 2009
  • Construction end2 weeks earlyforecast Jul 31, 2010

Also in Callander

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30488 in the federal list. How to read these figures.