Standby Power Generation
Federal contribution
$100,000
Federal share33%
of $300.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of Callander
- Construction start
- Aug 31, 2009(actual)
- Construction end
- Jul 15, 2010(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 1, 2009
- Construction end2 weeks earlyforecast Jul 31, 2010
Also in Callander
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30488 in the federal list. How to read these figures.