Water Treatment Plant Improvements
Federal contribution
$655,000
Federal share33%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Town of Asquith
- Construction start
- Apr 28, 2010(actual)
- Construction end
- Oct 27, 2011(actual)
Also in Asquith