Water Main and Sewer Trunk Line for Town Expansion
Federal contribution
$219,723
Federal share33%
of $659.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Town of Asquith
- Construction start
- Aug 25, 2010(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start4 months lateforecast May 1, 2010
- Construction end4 months earlyforecast Jul 31, 2011
Also in Asquith