Improvement of Sprucegrove River Road in Charlton and Dack
Federal contribution
$28,350
Federal share45%
of $63.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedJan 29, 2010
2010
Built
Approved 8 months after the announcement.
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Municipality of Charlton and Dack
- Construction start
- May 31, 2010(actual)
- Construction end
- Aug 5, 2010(actual)
Against the original forecast
- Construction start4 weeks lateforecast May 3, 2010
- Construction end8 weeks earlyforecast Sep 30, 2010
Also in Englehart