Back to projects

Improvement of Sprucegrove River Road in Charlton and Dack

Englehart, Ontario

completeHighways and RoadsCC Top Up
Federal contribution
$28,350
Federal share45%

of $63.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedJan 29, 2010
2010
Built

Approved 8 months after the announcement.

Program
Building Canada Fund - Communities Component Top Up
Construction start
May 31, 2010(actual)
Construction end
Aug 5, 2010(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 3, 2010
  • Construction end8 weeks earlyforecast Sep 30, 2010

Also in Englehart

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27277 in the federal list. How to read these figures.