Back to projects

Renewal of Listowel Wastewater and Water Infrastructure

Listowel, Ontario

completeWastewaterCC Top Up
Federal contribution
$2.1M
$2,106,167
Federal share33%

of $6.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Municipality of North Perth
Construction start
Mar 25, 2010(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start10 months lateforecast Jun 5, 2009
  • Construction end7 months earlyforecast Oct 31, 2011

Also in Listowel