Schedule
Announced and approvedJun 5, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Municipality of North Perth
- Construction start
- Mar 25, 2010(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start10 months lateforecast Jun 5, 2009
- Construction end7 months earlyforecast Oct 31, 2011