Rehabilitation of North Perth Administration Building
Federal contribution
$1.2M
$1,186,029
Federal share33%
of $3.6M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of North Perth
- Construction start
- Dec 1, 2009(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start4 weeks lateforecast Nov 3, 2009
Also in Listowel
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31790 in the federal list. How to read these figures.