Watermain Replacement & Paving

Eatonia, Saskatchewan

completeDrinking WaterCC Top Up
Federal contribution
$156,231
Federal share33%

of $468.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Town of Eatonia
Construction start
Apr 27, 2010(actual)
Construction end
Nov 12, 2010(actual)

Against the original forecast

  • Construction end5 months earlyforecast Mar 31, 2011

Also in Eatonia

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27326 in the federal list. How to read these figures.