Raw Water Main Replacement
Federal contribution
$261,262
Federal share50%
of $522.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 11, 2017
2017
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Eatonia
- Construction start
- Aug 8, 2017(actual)
- Construction end
- Oct 3, 2017(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 1, 2017
- Construction end18 months earlyforecast Mar 31, 2019
Also in Eatonia
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48426 in the federal list. How to read these figures.