Replacement of Highway 17 Sewer and Waterlines

Mattawa, Ontario

completeDrinking WaterCC Top Up
Federal contribution
$1.5M
$1,522,964
Federal share33%

of $4.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Town of Mattawa
Construction start
Aug 1, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jul 1, 2010