Reconstruction of Dorion Road Hill
Federal contribution
$2.9M
$2,870,400
Federal share60%
of $4.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 28, 2020
today
2021202320252027
BuiltForecast
Approved 4 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Mattawa
- Construction start
- Aug 21, 2023(actual)
- Construction end
- Oct 31, 2026(forecast)
Also in Mattawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54584 in the federal list. How to read these figures.