Rehabilitation of Barry Cooper Road
Federal contribution
$543,686
Federal share33%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Township of Madoc
- Construction start
- Jul 30, 2009(actual)
- Construction end
- Jul 31, 2010(actual)
Also in Madoc
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27382 in the federal list. How to read these figures.