Reconstruction of Springbrook Road West of Highway 62
Federal contribution
$295,637
Federal share33%
of $886.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Municipality of Centre Hastings
- Construction start
- Sep 1, 2009(actual)
- Construction end
- Oct 15, 2010(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Sep 20, 2009
- Construction end11 months lateforecast Nov 15, 2009
Also in Madoc
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27830 in the federal list. How to read these figures.