Extension of Rural Road #2

Englehart, Ontario

completeHighways and RoadsCC Top Up
Federal contribution
$30,866
Federal share45%

of $68.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
Jul 12, 2010(actual)
Construction end
Nov 30, 2010(actual)

Against the original forecast

  • Construction start9 months lateforecast Oct 1, 2009

Also in Englehart