Back to projects

Water and Sewer Installation - Ridge Road

Holyrood, Newfoundland and Labrador

completeDrinking WaterCC
Federal contribution
$243,961
Federal share33%

of $731.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 14, 2009
2010
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Holyrood
Construction start
Jun 5, 2010(actual)
Construction end
Oct 28, 2010(actual)

Against the original forecast

  • Construction start8 months lateforecast Oct 15, 2009
  • Construction end8 months lateforecast Mar 1, 2010

Also in Holyrood

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27527 in the federal list. How to read these figures.