Construction of Woodstock Art Gallery and Community Arts Centre

Woodstock, Ontario

completeCultureCC Top Up
Federal contribution
$1.5M
$1,478,051
Federal share33%

of $4.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
City of Woodstock
Construction start
Mar 15, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Apr 5, 2010
  • Construction end3 months lateforecast Jul 22, 2011