Schedule
Announced and approvedJun 5, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- City of Woodstock
- Construction start
- Mar 15, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Apr 5, 2010
- Construction end3 months lateforecast Jul 22, 2011