Bulk Item and Household Hazardous Waste Depot
Federal contribution
$666,667
Federal share33%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 25, 2015
201620172018
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Woodstock
- Construction start
- May 15, 2017(actual)
- Construction end
- Dec 11, 2017(actual)
Against the original forecast
- Construction start12 months lateforecast May 1, 2016
- Construction end3 months lateforecast Sep 15, 2017
Also in Woodstock
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46205 in the federal list. How to read these figures.