Reconstruction of Concession Road #2

Prescott, Ontario

completeHighways and RoadsCC Top Up
Federal contribution
$814,815
Federal share33%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Township of Augusta
Construction start
Jun 1, 2010(actual)
Construction end
Oct 25, 2010(actual)

Against the original forecast

  • Construction start2 weeks lateforecast May 17, 2010
  • Construction end6 weeks lateforecast Sep 15, 2010

Also in Prescott