Reconstruction of Concession Road #2
Federal contribution
$814,815
Federal share33%
of $2.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Township of Augusta
- Construction start
- Jun 1, 2010(actual)
- Construction end
- Oct 25, 2010(actual)
Against the original forecast
- Construction start2 weeks lateforecast May 17, 2010
- Construction end6 weeks lateforecast Sep 15, 2010
Also in Prescott