Prince Street Rehabilitation Program
Federal contribution
$371,492
Federal share31%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Prescott
- Construction start
- Aug 27, 2010(actual)
- Construction end
- Sep 1, 2011(actual)
Against the original forecast
- Construction start8 weeks lateforecast Jun 30, 2010
- Construction end4 weeks lateforecast Aug 5, 2011