Rehabilitation of Ski Hill and Mountainview Roads
Federal contribution
$28,527
Federal share33%
of $85.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Township of Nipissing
- Construction start
- Sep 21, 2009(actual)
- Construction end
- Oct 5, 2009(actual)
Against the original forecast
- Construction start2 months lateforecast Jul 15, 2009