Ventilation Upgrade of Community Centre & Office

Nipissing, Ontario

completeVentilationCVRIS
Federal contribution
$44,000
Federal share80%

of $55.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 15, 2021
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Township of Nipissing
Construction start
Jul 9, 2021(actual)
Construction end
Aug 16, 2021(actual)

Against the original forecast

  • Construction start2 months lateforecast May 10, 2021
  • Construction end6 weeks earlyforecast Sep 30, 2021

Also in Nipissing

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58952 in the federal list. How to read these figures.