Improvements to Hearst Community Curling Club

Hearst, Ontario

completeRecreationCC Top Up
Federal contribution
$650,650
Federal share33%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
Nov 10, 2010(actual)
Construction end
Oct 30, 2011(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Oct 15, 2010

Also in Hearst

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27739 in the federal list. How to read these figures.