Club Action Hearst Community Centre
Federal contribution
$692,333
Federal share33%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 21, 2009
20102011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Club Action Hearst
- Construction start
- Sep 6, 2010(actual)
- Construction end
- Sep 20, 2011(actual)
Against the original forecast
- Construction start5 weeks lateforecast Aug 3, 2010
- Construction end6 weeks earlyforecast Oct 31, 2011
Also in Hearst
- Rehabilitation and improvements to the Hearst Claude-Larose Recreation Centre$1.9M
- Improvements to Hearst Community Curling Club$650.6K
- Rehabilitation of Hearst Drinking Water Plant Disinfection Reservoirs$545.8K
- Rehabilitation of the Hearst Water Treatment Plant$390.7K
- Allen Street Rehabilitation$327.9K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33037 in the federal list. How to read these figures.