Reconstruction of Alexander Street

Pembroke, Ontario

completeHighways and RoadsCC Top Up
Federal contribution
$829,880
Federal share33%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
City of Pembroke
Construction start
Sep 13, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Aug 18, 2010