Improvements to Port McNicoll Wastewater Treatment Plant Capacity
Federal contribution
$2.1M
$2,072,078
Federal share33%
of $6.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Township of Tay
- Construction start
- Sep 1, 2009(actual)
- Construction end
- Oct 31, 2009(actual)
Against the original forecast
- Construction start4 weeks lateforecast Aug 4, 2009
- Construction end2 years earlyforecast Oct 31, 2011
Also in Victoria Harbour