Ceremonial Round House/Community Centre - Enaahtig Healing Lodge and Learning Centre

Victoria Harbour, Ontario

completeRecreationISF
Federal contribution
$252,000
Federal share33%

of $756.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 21, 2009
20102011
Built
Program
Infrastructure Stimulus Fund
Construction start
Nov 3, 2010(actual)
Construction end
Nov 25, 2011(actual)

Against the original forecast

  • Construction start3 months lateforecast Jul 31, 2010
  • Construction end4 weeks lateforecast Oct 31, 2011

Also in Victoria Harbour

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35570 in the federal list. How to read these figures.