Sooke - Boat Launch Construction

Sooke, British Columbia

completeRecreationCC Top Up
Federal contribution
$302,884
Federal share33%

of $908.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
District of Sooke
Construction start
Dec 20, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Nov 30, 2010

Also in Sooke

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27961 in the federal list. How to read these figures.