New Reservoir
Federal contribution
$234,341
Federal share33%
of $703.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 6, 2009
200920102011
Built
Approved 8 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Village of Canning
- Construction start
- Oct 1, 2009(actual)
- Construction end
- Mar 29, 2011(actual)
Against the original forecast
- Construction start5 months lateforecast May 1, 2009