Chapel Road Water Upgrades

Canning, Nova Scotia

underwayWastewaterRNIS
Federal contribution
$982,400
Federal share28%

of $3.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 22, 2022
today
2023202420252026
BuiltForecast

Approved 2 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Village of Canning
Construction start
Jul 14, 2025(actual)
Construction end
Sep 30, 2026(forecast)

Against the original forecast

  • Construction start3 months lateforecast Apr 1, 2025