Back to projects

Storm Sewer Separation - West Side

New Glasgow, Nova Scotia

completeWastewaterCC
Federal contribution
$273,940
Federal share33%

of $821.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 11, 2009
2009
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of New Glasgow
Construction start
Jun 1, 2009(actual)
Construction end
Dec 10, 2009(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Jul 1, 2009
  • Construction end16 months earlyforecast Mar 31, 2011

Also in New Glasgow

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28165 in the federal list. How to read these figures.