New R.O. Filtration System - WTP

Luseland, Saskatchewan

completeDrinking WaterCC
Federal contribution
$419,066
Federal share33%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2009
2010201120122013
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Luseland
Construction start
Aug 15, 2011(actual)
Construction end
May 31, 2013(actual)

Against the original forecast

  • Construction start15 months lateforecast May 1, 2010
  • Construction end10 months earlyforecast Mar 31, 2014

Also in Luseland

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28262 in the federal list. How to read these figures.