New Wastewater Mains and Pump Station

Luseland, Saskatchewan

completeWastewaterCWWF
Federal contribution
$280,000
Federal share50%

of $560.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 2, 2017
20182019
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Luseland
Construction start
Sep 25, 2017(actual)
Construction end
Jan 31, 2019(actual)

Against the original forecast

  • Construction start6 months lateforecast Apr 1, 2017
  • Construction end4 weeks lateforecast Dec 31, 2018

Also in Luseland

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50043 in the federal list. How to read these figures.