Back to projects

Improvements to the Bicycle Path

Saint-Lazare-de-Bellechasse, Quebec

completeActive TransportationCC
Federal contribution
$259,721
Federal share33%

of $792.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 3, 2009
Built

Approved 4 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Construction start
Jul 1, 2009(actual)
Construction end
Dec 1, 2009(actual)

Also in Saint-Lazare-de-Bellechasse

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28265 in the federal list. How to read these figures.