Repairs to the Monseigneur Bilodeau Storm Sewer (phase 2) and Replacement of a Culvert
Saint-Lazare-de-Bellechasse, Quebec
Federal contribution
$104,830
Federal share33%
of $314.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 8, 2011
2011
Built
Approved 13 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of Saint-Lazare-de-Bellechasse
- Construction start
- Sep 21, 2010(actual)
- Construction end
- Jul 31, 2011(actual)
Against the original forecast
- Construction start5 weeks lateforecast Aug 15, 2010
Also in Saint-Lazare-de-Bellechasse
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40658 in the federal list. How to read these figures.