Reconstruction of Urban Infrastructure - Sheffort Street

Bromont, Quebec

completeDrinking WaterCC
Federal contribution
$1.2M
$1,212,891
Federal share33%

of $3.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 15, 2009
20102011201220132014
Built

Approved 7 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Bromont
Construction start
Apr 1, 2011(actual)
Construction end
Mar 31, 2014(actual)

Against the original forecast

  • Construction start22 months lateforecast Jun 15, 2009
  • Construction end3.8 years lateforecast Jun 28, 2010

Also in Bromont

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28270 in the federal list. How to read these figures.