Water Systems Upgrade

Bromont, Quebec

completeWastewaterGIS
Federal contribution
$820,342
Federal share40%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
202120222023
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Bromont
Construction start
Oct 7, 2020(actual)
Construction end
Aug 31, 2023(actual)

Against the original forecast

  • Construction end9 months lateforecast Dec 15, 2022